The Bentleigh – Construction Update 2017

By Dongmei Liu

March Update:

  • The basement slab now completed
  • Ground slab scheduled to be completed by end of March
  • Estimated completion in fourth quarter of 2017

Jan Update:

The following are the current update for project  Bentleigh,
  • Piling completed
  • Bulk excavation 70% completed
  • Footings (in process)
  • S2 permit conditions all met – need BOE (in process)
  • Precast end of Feb
  • Next package roof, Plaster, cladding

The completion for this project is estimated late 2017.

Up to Date

Latest News

  • A Little Ray of Giving

    This Christmas, Ray White Southbank will continue its popular local tradition of giving to those less fortunate with the return of “A Little Ray of Giving”. This inspiring Christmas campaign will see Ray White Southbank partner with the Rotary Club of Southbank to help disadvantaged children who may need a … Read more

    Read Full Post

  • BUSTING THREE COMMON PROPERTY MANAGEMENT MYTHS

    Generating passive income from property is a dream for many Australians. The average rental price for a house in our country is $555 – imagine earning that from your investment week in and week out without spending a single extra hour at work. It’s certainly possible, but unfortunately investment isn’t … Read more

    Read Full Post