The Bentleigh – Construction Update 2017

By Dongmei Liu

March Update:

  • The basement slab now completed
  • Ground slab scheduled to be completed by end of March
  • Estimated completion in fourth quarter of 2017

Jan Update:

The following are the current update for project  Bentleigh,
  • Piling completed
  • Bulk excavation 70% completed
  • Footings (in process)
  • S2 permit conditions all met – need BOE (in process)
  • Precast end of Feb
  • Next package roof, Plaster, cladding

The completion for this project is estimated late 2017.

Up to Date

Latest News

  • BUSTING THREE COMMON PROPERTY MANAGEMENT MYTHS

    Generating passive income from property is a dream for many Australians. The average rental price for a house in our country is $555 – imagine earning that from your investment week in and week out without spending a single extra hour at work. It’s certainly possible, but unfortunately investment isn’t … Read more

    Read Full Post

  • Happy Easter – Easter Trading Hours

    With the Easter public holiday period ahead of us we would like to update you on our Easter Trading Hours. Our opening hours over the holiday period are as follows: Our office will be closed from 5.30pm Thursday, 13th April 2017 and re-opening Tuesday, 18th April 2017. For any urgent … Read more

    Read Full Post